Hello All,
As per our previous announcement all parties have confirmed access and we are set to move compute, to confirm below is an updated ETA
The Logistics: I (Aaran) will personally be on-site at Telford at 9:00 AM to oversee the process.
09:00 - 11:00: Safe de-racking and loading of hardware.
11:00 - 12:00: Transit to the new Wolverhampton facility.
12:00 - 14:00: Re-racking, powering up, and bringing the core network online.
We have planned for a 6-hour total outage window to account for any traffic or unforeseen delays, though we are optimistic that services will be restored sooner (aiming for 3-4 hours).
Regards,
Aaran P
Company Director
HYEHOST LLC